Ineffective controls preventing access to railway tracks
First to latest report 27 May 2015 — 4 Mar 2024
Reports that mention this concern
24
Times this concern has been raised
31
Stated actions linked to this concern
60
What this concern includes
Includes failures of controls specifically dedicated to preventing or restricting access to railway tracks, including physical barriers or mitigation measures and responses to identified railway-access risks or recommended remedial actions.
What is not included
Excludes generic failures in investigation, documentation, training, staffing or governance unless they are directly tied to a dedicated railway-track-access control.
Excludes railway hazards unrelated to preventing access to the tracks.
Excludes general infrastructure or highway safety deficiencies that do not concern access to railway tracks.
Trends
Reports over time
Reports mentioning this concern, over time
Reports about this concern issued each year.
* 2026 is projected from reports observed to 7 Sep 2026.
Most frequent recipients
Most frequent recipients
Reports about this concern sent to each recipient.
Network Rail21
British Transport Police3
Alexandra Park and Palace Charitable Trust1
Arriva Rail North Limited1
Broxtowe Borough Council1
Department for Education1
Derbyshire County Council1
Erewash Borough Council1
Father of the deceased1
First MTR South Western Trains Limited1
London Borough of Hackney1
London North Eastern Railway Limited1
London & South Eastern Railway Limited1
Mother of the deceased1
Nottinghamshire County Council1
Rail infrastructure manager21
Train operating company4
Special police force3
English county council1
English district council1
London borough council1
Ministerial department1
Private limited company1
Rail safety body1
Registered charity1
Type not available1
Reports and published responses 24 reports
See individual reports that have raised this concern, and the actions taken in response
Bedfordshire and Luton
Concerns raised1
Inadequate physical barriers at the railway access gate
No linked response statements
No respondent-stated action or position is linked to these concerns in the published data.
Inner South London
Concerns raised1
Failure to restrict public access to the railway
This report raised 1 other concern. They are not shown here because they do not form part of this recurring concern.
Linked response
Network Rail Infrastructure Limited
Stated actions An action is something a respondent says it has done, is doing, or plans to do in response to the concern raised.4
Network Rail Infrastructure Limited
Replace the old footbridge with a safer structure incorporating standard-height railings, an encased railway span, ramps, safer pedestrian exits and no mid-elevation turnback.
Network Rail Infrastructure Limited
Install three-metre acoustic fencing with anti-climb extensions along both sides of the track and adjacent to Mottistord Road.
Network Rail Infrastructure Limited
Install anti-climb guards above the footbridge railings at the steps, ramps and main span.
Network Rail Infrastructure Limited
Remove old building materials from beneath the footbridge.
Manchester West
Concerns raised1
Inadequate restriction of public access to the railway track from the steps accessing footbridge 57
Linked response
Network Rail Infrastructure Limited
Stated actions An action is something a respondent says it has done, is doing, or plans to do in response to the concern raised.2
Network Rail Infrastructure Limited
Install shorter palisade pales on the lower flight to connect with the boundary fence and raise the parapet to at least two metres.
Network Rail Infrastructure Limited
Raise the upper-flight stepped parapet with engineering brick and bullnose units to prevent scaling and access behind the lower-flight palisade.
Inner South London
Concerns raised1
Failure of after-hours station and track access barriers to prevent access
Linked response
Network Rail Infrastructure Limited
Stated actions An action is something a respondent says it has done, is doing, or plans to do in response to the concern raised.1
Network Rail Infrastructure Limited
Install barriers to separate rail infrastructure where access is unnecessary, including fencing SouthEastern infrastructure from LOROL infrastructure at the station.
Respondent positions A position is what a respondent says about the concern when they do not describe a specific action.2
Network Rail Infrastructure Limited
Station access and management are outside the infrastructure owner's management because the station is operated by the train operator.
Outside remitThe respondent said that this matter was outside its role or authority.
Network Rail Infrastructure Limited
Responsibility for station access information and practices rests with the station operator, which provided the relevant clarification.
Redirects responsibilityThe respondent said that another organisation was responsible for deciding or taking action.
Actions and positions describe what organisations say in published responses. Implementation is not independently verified.