Failure to prevent unauthorised access to operational sites
First to latest report 22 Jun 2018 — 25 Aug 2020
Reports that mention this concern
2
Times this concern has been raised
2
Stated actions linked to this concern
7
What this concern includes
Includes failures of controls dedicated to preventing, detecting or responding to unauthorised entry or occupation of operational sites, including physical access controls, security presence, site checks, detection of unauthorised occupants and action to secure the site.
What is not included
Excludes authorised access, ordinary site use and security arrangements where no unauthorised-entry or occupation risk is identified.
Excludes hazards inside an operational site where access control is not the deficient condition.
Excludes public access to closed or restricted hazardous sites where the existing narrower hazardous-site access concern is the more faithful boundary.
Excludes generic staffing, communication or supervision deficiencies unless they directly impair prevention or detection of unauthorised access or occupation.
Trends
Reports over time
Reports mentioning this concern, over time
Reports about this concern issued each year.
* 2026 is projected from reports observed to 7 Sep 2026.
Most frequent recipients
Most frequent recipients
Reports about this concern sent to each recipient.
Canary Wharf Group PLC1
First Response Group1
London Borough of Camden1
Company1
London borough council1
Public limited company1
Reports and published responses 2 reports
See individual reports that have raised this concern, and the actions taken in response
Inner North London
Concerns raised1
Failure to detect unauthorised occupation of operational sites
This report raised 5 other concerns. They are not shown here because they do not form part of this recurring concern.
Linked response
London Borough of Camden
Stated actions An action is something a respondent says it has done, is doing, or plans to do in response to the concern raised.4
London Borough of Camden
Review development properties and inspect them for unauthorised access or use.
London Borough of Camden
Obtain approval and implement a standard Site Security Scope of Service across contracts requiring contracted security.
London Borough of Camden
Require security contractors to submit weekly site-activity and sign-in/out reports to the Council’s project team.
London Borough of Camden
Work with relevant departments to assess ways of making void properties less attractive or habitable to trespassers.
Respondent positions A position is what a respondent says about the concern when they do not describe a specific action.2
London Borough of Camden
First Response is best placed to respond to concerns about its employees’ evidence and conduct at the site.
Redirects responsibilityThe respondent said that another organisation was responsible for deciding or taking action.
London Borough of Camden
Existing site security arrangements were considered suitable based on property reviews and comprehensive controls already operating at Aspen House.
Existing arrangements considered sufficientThe respondent said that existing arrangements were sufficient, so no further action was needed.
Inner North London
Concerns raised1
Failure to secure the turnstile against unauthorised access
This report raised 2 other concerns. They are not shown here because they do not form part of this recurring concern.
Linked response
Canary Wharf Contractors Ltd
Stated actions An action is something a respondent says it has done, is doing, or plans to do in response to the concern raised.3
Canary Wharf Contractors Ltd
Raise the turnstile base with a robust plywood ramp, reducing the access gap from 30cm to 20cm.
Canary Wharf Contractors Ltd
Install temporary solid panels inside turnstile pods at the end of each day shift to prevent out-of-hours unauthorised access.
Canary Wharf Contractors Ltd
Adopt comparable turnstile security measures on future projects where access is directly from public areas.
Respondent positions A position is what a respondent says about the concern when they do not describe a specific action.2
Canary Wharf Contractors Ltd
The turnstile gap was reduced by 10 centimetres, not 5 centimetres, following Samuel’s death.
Disputes the concernThe respondent disagreed with part of the concern or the basis for it.
Canary Wharf Contractors Ltd
The reduced turnstile gap was considered a sufficient control measure, and the inspector required no further action.
Existing arrangements considered sufficientThe respondent said that existing arrangements were sufficient, so no further action was needed.
Actions and positions describe what organisations say in published responses. Implementation is not independently verified.