First reported 22 Oct 2015•Latest report 24 Nov 2020
Definition
What this concern includes
Includes failures in the dedicated lifting-operation process, including identifying the actual lifting method, preparing and agreeing a suitable lift plan or risk assessment, specifying load orientation and handling instructions, defining stop conditions and required supervision, and ensuring the plan is approved and communicated before work begins.
Not included
Excludes generic work-method, training, communication or safety-management deficiencies where no lifting-operation planning or control failure is identified.
Excludes equipment design, maintenance or inspection failures where the lifting operation's planning and control process is not deficient.
Excludes failures in loading or transport operations that do not involve lifting operations or their dedicated safety controls.
Excludes implementation failures occurring after a complete, approved and communicated lifting plan has been established, unless the plan or its control arrangements were themselves inadequate.
Reports
2
Distinct published reports
Individual concerns
4
A report can raise multiple concerns
Date range
2015–2020
First to latest report issue date
Stated actions
8
Described in published responses
Reports over time
Reports over time
Reports about this concern issued each year.
* 2026 is projected from reports observed to 7 Sep 2026.
Most frequent recipients
Most frequent recipients
Reports about this concern sent to each recipient.
C.M.F. Limited1
Laing O'Rourke1
PCR Steel Ltd1
Recipient name withheld1
SE Galvanisers Ltd1
Private limited company2
Public limited company1
Type not available1
Concerns and responses across reports
Only concerns grouped under this recurring concern are included. Select any concern, action or position to view the source wording.
Essex
Concerns raised1
Lack of an approved and agreed loading and lifting plan
This report raised 3 other concerns. They are not shown here because they do not form part of this recurring concern.
Responses linked to these concerns
Each statement is shown once, even when linked to more than one concern.
No linked response statements
No respondent-stated action or position is linked to these concerns in the published data.
Inner North London
Concerns raised3
Failure of method statements, risk assessments and lift plans to address changed landing-fitting processes
Failure to specify the correct landing orientation for tag-line tilting
Failure to include stop instructions for unsuccessful positive fixings during landing fitting
This report raised 3 other concerns. They are not shown here because they do not form part of this recurring concern.
Responses linked to these concerns
Each statement is shown once, even when linked to more than one concern.
Actions described in response An action is something a respondent says it has done, is doing, or plans to do in response to the concern raised.8
Action
Review all package method statements and lifting plans, suspend lifting plans pending review, and reapprove them before work recommences.
Stated by Laing O’Rourke PlcStated completedThe respondent said that this action was complete when they made their response on 22 October 2015.
Action
Require monthly review of higher-risk activities and Planned-versus-Actual assessments against accepted methods.
Stated by Laing O’Rourke PlcStated completedThe respondent said that this action was complete when they made their response on 22 October 2015.
Action
Use purpose-designed lifting holes or bespoke lifting carriages, identified during design with advice from the appointed person.
Stated by C.M.F. LimitedStated plannedThe respondent said that this action was planned when they made their response on 22 October 2015.
Action
Require qualified appointed persons to plan lifting operations using CMF’s native lift-plan procedure.
Stated by C.M.F. LimitedStated plannedThe respondent said that this action was planned when they made their response on 22 October 2015.
Action
Submit lifting plans, temporary-works requirements and relevant design considerations to the Principal Contractor for approval before lifting.
Stated by C.M.F. LimitedStated plannedThe respondent said that this action was planned when they made their response on 22 October 2015.
Action
Implement an alternative landing-lifting method using bolted lifting frames, anchored lifting eyes, chains, separate winches and an additional slab opening.
Stated by C.M.F. LimitedStated completedThe respondent said that this action was complete when they made their response on 22 October 2015.
Action
Require positive lifting attachments for landings and staircases and request detailed RAMS for removing damaged landings.
Stated by Laing O’Rourke PlcStated completedThe respondent said that this action was complete when they made their response on 22 October 2015.
Action
Stop lifting when circumstances, environmental changes or attachment deviations compromise the operation, then assess and approve lift-plan modifications before resuming.
Stated by C.M.F. LimitedStated plannedThe respondent said that this action was planned when they made their response on 22 October 2015.
Respondent positions A position is what a respondent says about the concern when they do not describe a specific action.4
Position
Responsibility for designing and planning the specialist lifting method and lift plan rested with the specialist contractor.
Stated by Laing O’Rourke PlcRedirects responsibilityThe respondent said that another organisation was responsible for deciding or taking action.
Position
The irregular landing shape was not sufficiently significant to require changing the lifting plan, and factory trials raised no concerns.
Stated by C.M.F. LimitedDisputes the concernThe respondent disagreed with part of the concern or the basis for it.
Position
The approved lift plan required positive attachments, and any inability to comply required lifting to stop and the plan to be reconsidered.
Stated by Laing O’Rourke PlcDisputes the concernThe respondent disagreed with part of the concern or the basis for it.
Position
Requiring positive lifting attachments was considered sufficient to ensure a safe system for lifting and manipulating the loads.
Stated by Laing O’Rourke PlcExisting arrangements considered sufficientThe respondent said that existing arrangements were sufficient, so no further action was needed.