What this concern includes
Includes dedicated prison processes for inspecting cell fabric and related safety features, assessing changing cell risks, recording and communicating findings, assigning remedial action and checking that identified concerns are addressed. This includes the anchor's failure of daily and weekly cell fabric checks and the separate failure to maintain robust cell-safety audits and act on identified concerns.
What is not included
- Excludes the underlying presence of a ligature point or other cell hazard when no failure of the prison cell inspection, risk-assessment or follow-up process is identified.
- Excludes generic prison staffing, communication, training or maintenance deficiencies unless they directly impair prison cell safety inspection, risk assessment or follow-up.
- Excludes broader suicide and self-harm prevention, prisoner observation or ACCT failures where the prison cell inspection and risk-assessment process is not the deficient control.
- Excludes ward, hospital, residential and non-prison premises inspections unless the assertion explicitly concerns the same prison cell safety process.
Trends
Reports over time
Reports mentioning this concern, over time
Reports about this concern issued each year.
* 2026 is projected from reports observed to 7 Sep 2026.
Most frequent recipients
Most frequent recipients
Reports about this concern sent to each recipient.
Reports and published responses 5 reports
See individual reports that have raised this concern, and the actions taken in response
-
Concerns raised1
Failure of daily accommodation and fabric checks to identify disrepair in special cells
This report raised 3 other concerns. They are not shown here because they do not form part of this recurring concern.
Linked response
- HM Prison and Probation Service
Stated actions An action is something a respondent says it has done, is doing, or plans to do in response to the concern raised.1
-
HM Prison and Probation Service
Remind Pentonville staff to complete daily accommodation fabric checks, including checks for items that could be used to ligature.
-
Concerns raised1
Delays in addressing identified cell-safety concerns
This report raised 6 other concerns. They are not shown here because they do not form part of this recurring concern.
Linked response
- HM Prison and Probation Service
Stated actions An action is something a respondent says it has done, is doing, or plans to do in response to the concern raised.3
-
HM Prison and Probation Service
Restore ligature-resistant cells to serviceable condition using approved lockable observation hatches.
-
HM Prison and Probation Service
Carry out daily accommodation fabric checks with additional scrutiny for cell damage or deterioration.
-
HM Prison and Probation Service
Remove cells with significant defects from use and document and monitor remedial work until they are serviceable.
-
Concerns raised1
Lack of in-cell ligature point risk assessments
This report raised 3 other concerns. They are not shown here because they do not form part of this recurring concern.
Linked response
- HM Prison and Probation Service
Respondent positions A position is what a respondent says about the concern when they do not describe a specific action.1
-
HM Prison and Probation Service
Existing observation escalation and gated-cell relocation are relied on to manage high-risk prisoners.
-
Concerns raised2
Lack of a formal process for communicating and acting on prison cell risk assessment results
Failure of daily and weekly cell fabric checks to identify risks
This report raised 3 other concerns. They are not shown here because they do not form part of this recurring concern.
Linked responses
- Birmingham and Solihull Mental Health NHS Foundation Trust
- HM Prison and Probation Service
Stated actions An action is something a respondent says it has done, is doing, or plans to do in response to the concern raised.3
-
Birmingham and Solihull Mental Health NHS Foundation Trust
Formalise the risk-assessment process with the prison by placing it on the Local Delivery Board meeting agenda.
-
HM Prison and Probation Service
Visit cells six months after NHS assessments to identify and minimise obvious ligature points.
-
HM Prison and Probation Service
Review ligature-resistant cells, including cell standards and regular maintenance requirements.
Respondent positions A position is what a respondent says about the concern when they do not describe a specific action.1
-
Birmingham and Solihull Mental Health NHS Foundation Trust
The prison, not the Trust, is responsible for implementing actions from prison risk assessments, including repairs and fabric upgrades.
-
Concerns raised1
Failure of regular maintenance checks to identify defective anti-barricade doors
This report raised 12 other concerns. They are not shown here because they do not form part of this recurring concern.
No linked response statementsNo respondent-stated action or position is linked to these concerns in the published data.
Actions and positions describe what organisations say in published responses. Implementation is not independently verified.
Data last updated 7 September 2026