Recurring concern

Unreliable highway-defect investigation and prioritisation

Pin Get email alerts Request correction

First reported 23 Mar 2017•Latest report 27 Feb 2026

Definition

What this concern includes

Includes highway-authority processes for identifying, measuring, investigating, categorising, prioritising and deciding remedial action for carriageway and pavement defects, including threshold rules and consideration of road-user type or use where these affect safety prioritisation.

Not included

  • Excludes physical road, pavement, drainage, lighting, signage and barrier defects where no failure in defect investigation, categorisation or prioritisation is identified.
  • Excludes highway hazard reporting, inspection scheduling and completion of remedial works when the reported deficiency is not the defect-assessment or prioritisation decision itself.
  • Excludes generic road-design, maintenance or road-user safety concerns without a material highway-defect investigation or prioritisation failure.
  • Excludes failures confined to a named hazard-specific process, such as flooding, roadside obstacles or road-junction safety, when defect investigation and prioritisation are not the shared unsafe condition.
Reports
5

Distinct published reports

Individual concerns
8

A report can raise multiple concerns

Date range
2017–2026

First to latest report issue date

Stated actions
13

Described in published responses

Reports over time

Reports over time

Reports about this concern issued each year.

* 2026 is projected from reports observed to 7 Sep 2026.

Most frequent recipients

Most frequent recipients

Reports about this concern sent to each recipient.

Bury Borough Council1
Department for Transport1
East Sussex County Council1
Lancashire County Council1
Newport City Council1
Surrey County Council1

Concerns and responses across reports

Only concerns grouped under this recurring concern are included. Select any concern, action or position to view the source wording.

  1. Gwent

    AI-generated summary

    Brema Elizabeth VIRGO · Prevention of Future Deaths report

    This summary was generated using AI from the published report. Please read the original report for the complete account.

    Report summary

    Brema Elizabeth Virgo died after tripping over a raised manhole cover while walking on a pavement, sustaining a significant head injury. The report identified concerns that pavement-defect assessment methods may fail to reflect the full height of defects, meaning hazards may not be identified and remedial action may not be taken.

    Read the report on judiciary.uk

    Source evidence

    How this individual concern was interpreted

    PFD Monitor created a concise, searchable interpretation from the report wording shown below.

    PFD Monitor interpretation

    Failure to properly identify relevant pavement defects

    Wider context from the report

    “The methods used for assessing and interpreting height of the defects in pavements allows for circumstances to occur whereby the actual height of the entire defect may not be reflected. Relevant defects may not be properly identified resulting in preventative remedial action not being taken, which presents a risk of future deaths. ”

    Source location

    Brema Elizabeth VIRGO · Prevention of Future Deaths report
    Page 1 · concerns

    Open source report

    Source evidence

    How this individual concern was interpreted

    PFD Monitor created a concise, searchable interpretation from the report wording shown below.

    PFD Monitor interpretation

    Inadequate methods for assessing and interpreting pavement defect height

    Wider context from the report

    “The methods used for assessing and interpreting height of the defects in pavements allows for circumstances to occur whereby the actual height of the entire defect may not be reflected. Relevant defects may not be properly identified resulting in preventative remedial action not being taken, which presents a risk of future deaths. ”

    Source location

    Brema Elizabeth VIRGO · Prevention of Future Deaths report
    Page 1 · concerns

    Open source report

    Source evidence

    How this respondent action was interpreted

    PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

    PFD Monitor interpretation

    Review the Highway Maintenance Manual to consider whether alterations are necessary in response to the reported concern.

    Verbatim wording from the response

    “Whilst we consider that no immediate or short term changes need to be made, in view of the serious nature of the incident in question, Highways intend to undertake a review of the Highway Maintenance Manual to consider whether any alterations to this may be necessary in view of your comments. Should any changes be identified, these would need to be reviewed by senior managers and proceed through a cabinet approval process, before being ratified and implemented.”

    Source location

    Response from Newport City Council
    Page 2 · response
    Published 9 March 2026

    Open published response

    Source evidence

    How this respondent position was interpreted

    PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

    PFD Monitor interpretation

    No immediate or short-term changes are considered necessary because existing highway inspection, risk-assessment, and defect-recording arrangements address the concern.

    Verbatim wording from the response

    “I and other senior members of the Council’s highways department have given detailed consideration to the report and reviewed the Council’s Manual and methods with reference to the specific concern raised. We have concluded that we do not consider that any immediate or short term changes need to be made.”

    Source location

    Response from Newport City Council
    Page 1 · response
    Published 9 March 2026

    Open published response
  2. Lancashire and Blackburn with Darwen

    AI-generated summary

    Harry College · Prevention of Future Deaths report

    This summary was generated using AI from the published report. Please read the original report for the complete account.

    Report summary

    Harry Colledge, an 84-year-old man, died after his bicycle entered a crack in the carriageway on Island Lane, throwing him from the bicycle and causing fatal injuries. Concerns included highway operatives’ ability to identify defects hazardous to cyclists and the adequacy of maintaining road surfacing affected by natural movement and underlying geological features.

    Read the report on judiciary.uk

    Source evidence

    How this individual concern was interpreted

    PFD Monitor created a concise, searchable interpretation from the report wording shown below.

    PFD Monitor interpretation

    Failure of highway operatives to identify defects hazardous to cyclists

    Wider context from the report

    “1. Highway operatives gave evidence that their inspections primarily consider the impact of defects upon cars using that road surface. All gave evidence of no specific training or experience with regards to identifying defects which present a hazard to bicycle users, when expert evidence indicated that the Council’s statutory duty required reasonable steps to protect all road users which includes cyclists. The evidence of Council witnesses was unanimous that since Mr Colledge’s death, there has been no additional training, updates, briefings or policy reviews to offer further knowledge of operatives in safely assessing defects which pose risks to cyclists or road users other than car drivers. I consider there is a risk of future deaths of all cyclists if Highways Operatives are not able to identify defects on a carriageway which present a risk to cyclists as opposed to simply car users. ”

    Source location

    Harry College · Prevention of Future Deaths report
    Page 2 · concerns

    Open source report

    Source evidence

    How this respondent action was interpreted

    PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

    PFD Monitor interpretation

    Deliver and disseminate an incident debrief covering lessons learned, operational instructions, defect reporting, surface cracking and hazards to all road users.

    Verbatim wording from the response

    “1. Inquest Debrief”

    Source location

    Response from Lancashire County Council
    Page 1 · response
    Published 23 February 2024

    Open published response

    Source evidence

    How this respondent action was interpreted

    PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

    PFD Monitor interpretation

    Deliver approved toolbox-talk awareness training to all Highway Operatives, including defect impacts and procedures for reporting defects for assessment.

    Verbatim wording from the response

    “As outlined above, there is an instruction in place that Highway Operatives are not to be used for defect identification through the "find and fix" method of working, their capacity being limited to repairing additional defects to those directed where they can be seen within existing traffic management arrangements.”

    Source location

    Response from Lancashire County Council
    Page 4 · response
    Published 23 February 2024

    Open published response

    Source evidence

    How this respondent position was interpreted

    PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

    PFD Monitor interpretation

    Highway Operatives are not responsible for identifying defects; Highway Safety Inspectors and Technicians carry out the inspection regime.

    Verbatim wording from the response

    “Highway Operatives are not required to identify or assess any defect as set out in the Highway Safety Inspection Policy, however they are given the scope to repair additional defects they may see within the area of highway contained in any traffic management already in place.”

    Source location

    Response from Lancashire County Council
    Page 3 · response
    Published 23 February 2024

    Open published response
  3. East Sussex

    AI-generated summary

    Jennifer Ann DYER · Prevention of Future Deaths report

    This summary was generated using AI from the published report. Please read the original report for the complete account.

    Report summary

    Jennifer Ann DYER, aged 36, died after her bicycle collided with a van following contact with a defective pothole on the B2188. The pothole had a history of failed repairs and previous concerns about the danger it posed to road users. The report raises concern that its categorisation as a low-risk defect requires significant review, stating that the death was avoidable.

    Read the report on judiciary.uk

    Source evidence

    How this individual concern was interpreted

    PFD Monitor created a concise, searchable interpretation from the report wording shown below.

    PFD Monitor interpretation

    Failure to appropriately categorise pothole risks

    Wider context from the report

    “Under the East Sussex Highway Asset Inspection Manual, this pothole fell within the definition of Cat 3 - LOW for risk and remedial works. The definition is “Greater than 40mm and less than 59mm deep and at least 300mm in all directions”. Clearly, this pothole was the proximate cause of the death of a young woman, and the categorisation of potholes in East Sussex requires significant review, to prevent future avoidable deaths within the County. ”

    Source location

    Jennifer Ann DYER · Prevention of Future Deaths report
    Page 1 · concerns

    Open source report

    Source evidence

    How this respondent action was interpreted

    PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

    PFD Monitor interpretation

    Introduce an enhanced risk-based inspection process allowing defect categories and response times to reflect location, usage and assessed risk.

    Verbatim wording from the response

    “In May 2021 a revised Highway Inspection Manual introduced an enhanced risk assessment process where the highway inspector can consider other factors, such as the location of a defect and usage, as well as the defect category in determining whether a response is required or a different response time required. This means that, following the risk assessment, they are able to change the category of a defect such as changing a non-intervention defect to an intervention defect or reduce or increase the category response time if deemed appropriate. For example, if a category 3 pothole is located on the part of the carriageway cyclists are likely to use such as the nearside edge, this could be increased to a category 2 or 1 depending on risk assessment.”

    Source location

    Response from East Sussex County Council
    Page 2 · response
    Published 16 September 2022

    Open published response

    Source evidence

    How this respondent action was interpreted

    PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

    PFD Monitor interpretation

    Continue reviewing the effectiveness of the enhanced risk-based approach, including how it would have affected the incident.

    Verbatim wording from the response

    “- Continue to review the effectiveness of the implemented enhanced risk based approach and in particular review how it would have affected this case”

    Source location

    Response from East Sussex County Council
    Page 3 · response
    Published 16 September 2022

    Open published response

    Source evidence

    How this respondent position was interpreted

    PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

    PFD Monitor interpretation

    The enhanced risk-based inspection process makes a specific review of pothole categories unnecessary.

    Verbatim wording from the response

    “risk based approach to its safety inspection regimes which allows for a more flexible approach to determining risk for all road users and defect response times. This enables the inspector to change the categorisation of a pothole to include potholes for repair that do not meet the lowest category if required or to change the category of a pothole to a medium or high risk following an onsite risk assessment that now also considers location and road usage in addition to size and depth.”

    Source location

    Response from East Sussex County Council
    Page 3 · response
    Published 16 September 2022

    Open published response
  4. Manchester (North)

    AI-generated summary

    Mr Roger Hamer · Prevention of Future Deaths report

    This summary was generated using AI from the published report. Please read the original report for the complete account.

    Report summary

    Mr Roger Hamer fell from his bicycle on Bury New Road, suffering a traumatic brain injury and multiple fractures, and died in hospital from those injuries on 2 April 2016. The inquest jury found that a pothole probably caused his fall. Concerns included inadequate recording and monitoring of carriageway deterioration, a lack of paint markings around potholes, the absence of a duty-of-candour procedure for investigating significant incidents, and proposed highway-management thresholds that might increase risks to cyclists.

    Read the report on judiciary.uk

    Source evidence

    How this individual concern was interpreted

    PFD Monitor created a concise, searchable interpretation from the report wording shown below.

    PFD Monitor interpretation

    Failure to investigate carriageway defects below the 40mm threshold

    Wider context from the report

    “(4) The Highway Authority is in the process of adopting a new procedure for highway management (“the New Procedure”), apparently based upon Well-Managed Highway Infrastructure: a Code of Practice published by the Department for Transport in October 2016. With regards to defects in the carriageway, the Highway Authority’s current procedure for highway management has an intervention level of 40mm so that any defect which is found to be 40mm or greater is repaired. Under the New Procedure 40mm will be redefined as the “investigation level”, so that once a carriageway defect is greater than 40mm a highway inspector will investigate it and consider whether a repair is needed. If 40mm is specified in the New Procedure as the minimum threshold for investigation then defects which measure less than 40mm may not be investigated and defects of 40mm or above may not be repaired. Whilst I was informed that highway inspectors have a discretion under both the current and new procedures to repair defects which do not meet the intervention or investigation criteria the jury noted inconsistencies in the application of the current procedure and I consider that the New Procedure will increase the risk of future deaths, in particular to cyclists. ”

    Source location

    Mr Roger Hamer · Prevention of Future Deaths report
    Page 3 · concerns

    Open source report

    Source evidence

    How this individual concern was interpreted

    PFD Monitor created a concise, searchable interpretation from the report wording shown below.

    PFD Monitor interpretation

    Inconsistent application of the current highway-management procedure

    Wider context from the report

    “(4) The Highway Authority is in the process of adopting a new procedure for highway management (“the New Procedure”), apparently based upon Well-Managed Highway Infrastructure: a Code of Practice published by the Department for Transport in October 2016. With regards to defects in the carriageway, the Highway Authority’s current procedure for highway management has an intervention level of 40mm so that any defect which is found to be 40mm or greater is repaired. Under the New Procedure 40mm will be redefined as the “investigation level”, so that once a carriageway defect is greater than 40mm a highway inspector will investigate it and consider whether a repair is needed. If 40mm is specified in the New Procedure as the minimum threshold for investigation then defects which measure less than 40mm may not be investigated and defects of 40mm or above may not be repaired. Whilst I was informed that highway inspectors have a discretion under both the current and new procedures to repair defects which do not meet the intervention or investigation criteria the jury noted inconsistencies in the application of the current procedure and I consider that the New Procedure will increase the risk of future deaths, in particular to cyclists. ”

    Source location

    Mr Roger Hamer · Prevention of Future Deaths report
    Page 3 · concerns

    Open source report

    Source evidence

    How this individual concern was interpreted

    PFD Monitor created a concise, searchable interpretation from the report wording shown below.

    PFD Monitor interpretation

    Failure to repair carriageway defects at or above the 40mm threshold

    Wider context from the report

    “(4) The Highway Authority is in the process of adopting a new procedure for highway management (“the New Procedure”), apparently based upon Well-Managed Highway Infrastructure: a Code of Practice published by the Department for Transport in October 2016. With regards to defects in the carriageway, the Highway Authority’s current procedure for highway management has an intervention level of 40mm so that any defect which is found to be 40mm or greater is repaired. Under the New Procedure 40mm will be redefined as the “investigation level”, so that once a carriageway defect is greater than 40mm a highway inspector will investigate it and consider whether a repair is needed. If 40mm is specified in the New Procedure as the minimum threshold for investigation then defects which measure less than 40mm may not be investigated and defects of 40mm or above may not be repaired. Whilst I was informed that highway inspectors have a discretion under both the current and new procedures to repair defects which do not meet the intervention or investigation criteria the jury noted inconsistencies in the application of the current procedure and I consider that the New Procedure will increase the risk of future deaths, in particular to cyclists. ”

    Source location

    Mr Roger Hamer · Prevention of Future Deaths report
    Page 3 · concerns

    Open source report

    Source evidence

    How this respondent action was interpreted

    PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

    PFD Monitor interpretation

    Agree an overarching framework with Greater Manchester highway authorities for consistent risk-based inspection, repair and investigation approaches.

    Verbatim wording from the response

    “Bury Council in collaboration with the other 9 Greater Manchester Highway Authorities, are seeking to agree an “Overarching Framework of Agreed Principles” which would provide consistency of approach across the boundaries on the following matters: frequency and classification of highways, the risk based approach to safety inspections, the risk based approach to repair timescales, the investigative levels which would trigger the Highway inspector to apply the risk based matrix for assessing the risk.”

    Source location

    2017-0259-Response-by-Bury-Council
    Page 4 · response
    Published 7 November 2017

    Open published response

    Source evidence

    How this respondent action was interpreted

    PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

    PFD Monitor interpretation

    Maintain highway inspection procedures and systems in accordance with best-practice guidance.

    Verbatim wording from the response

    “1) Bury Council, as Highway Authority, ensured that their procedures and systems of inspection were in accordance with best practice guidance as set out within the Well Maintained Highways – A Code of Practice for Highway Maintenance Management 2009.”

    Source location

    2017-0259-Response-by-Bury-Council
    Page 1 · response
    Published 7 November 2017

    Open published response

    Source evidence

    How this respondent action was interpreted

    PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

    PFD Monitor interpretation

    Provide specific training and competency checks for highway inspectors under the new Code of Practice.

    Verbatim wording from the response

    “All Highway Inspectors are scheduled to undergo specific training and competency checks to ensure that they understand how to undertake their role under the new Code of Practice.”

    Source location

    2017-0259-Response-by-Bury-Council
    Page 4 · response
    Published 7 November 2017

    Open published response

    Source evidence

    How this respondent action was interpreted

    PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

    PFD Monitor interpretation

    Conduct regular evidence-based reviews and monitoring of the new Code of Practice.

    Verbatim wording from the response

    “The Highway Authority aim is to ensure consistency of approach in application of both the current and the new Code of Practice. The new risk based approach and specific training of inspectors on their role in accordance with the WMHI Code of Practice should allow the Highway Authority to apply a consistent risk based approach where the reasons for taking specific decisions will be evidenced. There will be regular evidence based reviews of the new Code of Practice and monitoring.”

    Source location

    2017-0259-Response-by-Bury-Council
    Page 4 · response
    Published 7 November 2017

    Open published response

    Source evidence

    How this respondent action was interpreted

    PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

    PFD Monitor interpretation

    Endorse the UK Roads Liaison Group code of practice for highway maintenance and management.

    Verbatim wording from the response

    “That said, the Department endorses a code of practice, issued by the UK Roads Liaison Group of which we are a member. This code of practice provides guidance to highway authorities on how to maintain and manage their highways: http://www.ukroadsliaisongroup.org/en/utilities/document-summary.cfm?docid=4F93BA10-D3B0-4222-827A8C48401B26AC”

    Source location

    2017-0259-Response-by-Department-for-Transport
    Page 1 · response
    Published 7 November 2017

    Open published response

    Source evidence

    How this respondent action was interpreted

    PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

    PFD Monitor interpretation

    Provide nearly £6 billion to local highway authorities in England outside London to improve local road condition.

    Verbatim wording from the response

    “I was very saddened to hear of the circumstances leading to Mr Hamer’s death. The Department for Transport considers the safety of all road users, including cyclists, a priority. The Government is providing just under £6 billion from 2015 to 2021 to allow local highway authorities in England, outside of London, to improve the condition of local roads across they are responsible for. In addition, we have topped this funding up with an extra £250 million specifically to tackle the blight of potholes.”

    Source location

    2017-0259-Response-by-Department-for-Transport
    Page 1 · response
    Published 7 November 2017

    Open published response

    Source evidence

    How this respondent action was interpreted

    PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

    PFD Monitor interpretation

    Provide an additional £250 million specifically to address potholes on local roads.

    Verbatim wording from the response

    “I was very saddened to hear of the circumstances leading to Mr Hamer’s death. The Department for Transport considers the safety of all road users, including cyclists, a priority. The Government is providing just under £6 billion from 2015 to 2021 to allow local highway authorities in England, outside of London, to improve the condition of local roads across they are responsible for. In addition, we have topped this funding up with an extra £250 million specifically to tackle the blight of potholes.”

    Source location

    2017-0259-Response-by-Department-for-Transport
    Page 1 · response
    Published 7 November 2017

    Open published response

    Source evidence

    How this respondent position was interpreted

    PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

    PFD Monitor interpretation

    Central Government cannot override local highway authorities’ decisions about highway maintenance, repair priorities or applicable standards.

    Verbatim wording from the response

    “However, as you will be aware, local highway authorities, in this case Bury Council, have a duty under Section 41 of the Highways Act 1980 to maintain the highways network in their area. The Act does not set out specific standards of maintenance, as it is for each individual local highway authority to assess which parts of their network are in need of repair and what standards should be applied, based upon their local knowledge and circumstances. Central Government has no powers to override local decisions in these matters.”

    Source location

    2017-0259-Response-by-Department-for-Transport
    Page 1 · response
    Published 7 November 2017

    Open published response

    Source evidence

    How this respondent position was interpreted

    PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

    PFD Monitor interpretation

    Local highway authorities are responsible for deciding highway repairs, maintenance standards and pothole dimensions based on local circumstances.

    Verbatim wording from the response

    “However, as you will be aware, local highway authorities, in this case Bury Council, have a duty under Section 41 of the Highways Act 1980 to maintain the highways network in their area. The Act does not set out specific standards of maintenance, as it is for each individual local highway authority to assess which parts of their network are in need of repair and what standards should be applied, based upon their local knowledge and circumstances. Central Government has no powers to override local decisions in these matters.”

    Source location

    2017-0259-Response-by-Department-for-Transport
    Page 1 · response
    Published 7 November 2017

    Open published response
  5. Surrey

    AI-generated summary

    Ralph Ian Brazier · Prevention of Future Deaths report

    This summary was generated using AI from the published report. Please read the original report for the complete account.

    Report summary

    Ralph Ian Brazier, a 52-year-old man, died after his bicycle struck a pothole next to a drainage gully cover on the A317 on 1 March 2016, throwing him onto the road. The concern was that Surrey County Council’s defect categorisation and repair priorities did not sufficiently account for cyclists using highways, particularly the nearside section of the road.

    Read the report on judiciary.uk

    Source evidence

    How this individual concern was interpreted

    PFD Monitor created a concise, searchable interpretation from the report wording shown below.

    PFD Monitor interpretation

    Failure to account for highway use by cyclists in highway-defect priority categorisations

    Wider context from the report

    “Having heard evidence from a number of members of Surrey County Council, I am concerned that insufficient consideration is taken by the Council of the increasing number of cyclists on their highways, particular in relation to the categorisation of defects on the highway. I am particularly concerned that designated cycle lanes are given higher priority relating to a defect than a highway, despite the high number of cyclists using the highway rather than cycle lanes with closer proximity to traffic including heavy goods vehicles. - Surrey County Council has failed to take into sufficient account the fact that cyclists use the highways as well as the cycle lanes in their priority categorisations. - That the great number of cyclists, and the risks to them using the highways, particularly the nearside section, are not specifically considered when Surrey County Council are assessing the highways for repair. Re-consideration should be given to whether any steps, including changes to the categorisation of highway defects in light of the greater use of public highways by cyclists, can be taken to address the above concerns. ”

    Source location

    Ralph Ian Brazier · Prevention of Future Deaths report
    Page 2 · concerns

    Open source report

    Source evidence

    How this respondent action was interpreted

    PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

    PFD Monitor interpretation

    Review the highway policy, analyse cyclists’ use of the network, and consider whether inspection, defect assessment, or categorisation should be amended.

    Verbatim wording from the response

    “The latest revision of the Code of Practice was published in October 2016 and in accordance with the revision of this national document SCC has begun a review of its highway policy. As part of this review SCC will also consider the Coroner’s concerns and if and to what extent the inspection regime, including defect assessment and categorisation, should be amended. This will include further analysis of the number of cyclists and differing use of the highway network by cyclists in Surrey. To allow for sufficient consideration of the revised national Code of Practice the authority has two years to make any amendments to their policies following its publication. On this basis the latest timeframe for implementation of any changes to our Highway Policy will be September 2018.”

    Source location

    2017-0090-Response-by-Surrey-County-Council_Redacted
    Page 2 · response
    Published 5 April 2017

    Open published response

    Source evidence

    How this respondent position was interpreted

    PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

    PFD Monitor interpretation

    Highway inspectors already consider risks to cyclists when assessing defects, and the relevant assessment complied with the highway policy.

    Verbatim wording from the response

    “In relation to the matter of assessment, highway inspectors, when assessing any defect in the highway, are required not only to apply the defect criteria set out in the policy but also to consider the particular circumstances of the locus including the potential danger created by the defect to all road users, cyclists as well as vehicle drivers. Cyclists are entitled to, and do, use all parts of Surrey’s road network. Highway Inspectors take this into account when assessing potential defects. ████████ the Highway Inspector who identified the defect scrutinised at the inquest, gave evidence that he took into account the potential dangers to cyclists when he categorised the defect. SCC is satisfied that ████████ assessment fully complied with its highway policy.”

    Source location

    2017-0090-Response-by-Surrey-County-Council_Redacted
    Page 2 · response
    Published 5 April 2017

    Open published response
Back to top