Recurring concern
Unreliable hospital emergency-power controls
First reported 17 Mar 2016•Latest report 21 Jul 2025
What this concern includes
Includes hospital controls for detecting, indicating, communicating, isolating, restoring or locally resetting emergency-power and related mains-power failures where loss of power can disrupt clinical treatment, equipment or patient safety, including EPO status indication and reset arrangements and alerts for local mains-power failure.
Not included
- Excludes ordinary electrical maintenance or equipment faults that are not part of hospital emergency-power detection, control or restoration arrangements.
- Excludes generic clinical escalation, staffing or communication failures unless they directly impair hospital emergency-power controls.
- Excludes failures of non-hospital power systems and routine building power use where no patient-safety consequence or emergency-power control is identified.
- Excludes downstream clinical treatment delays after emergency power has been reliably detected and restored.
- Reports
- 2
- Individual concerns
- 5
- Date range
- 2016–2025
- Stated actions
- 5
Distinct published reports
A report can raise multiple concerns
First to latest report issue date
Described in published responses
Reports over time
Reports over time
Reports about this concern issued each year.
* 2026 is projected from reports observed to 7 Sep 2026.
Most frequent recipients
Most frequent recipients
Reports about this concern sent to each recipient.
Concerns and responses across reports
Only concerns grouped under this recurring concern are included. Select any concern, action or position to view the source wording.
-
Concerns raised4
Unavailability of an in-room EPO circuit reset control
Lack of guidance on remote siting of Emergency Power Off controls
Accidental activation of Emergency Power Off circuits overriding emergency power backup systems
Lack of in-room indication of Emergency Power Off circuit activation
Responses linked to these concernsEach statement is shown once, even when linked to more than one concern.
Actions described in response An action is something a respondent says it has done, is doing, or plans to do in response to the concern raised.2
-
Action
Amend HBN 06-01 to address emergency-stop button locations and incorporate the discussed changes to EPO guidance.
Stated by NHS England -
Action
Update HTM 06-01, reviewing EPO content against the incident and HBN 06-01 to align the final guidance.
Stated by NHS England
Respondent positions A position is what a respondent says about the concern when they do not describe a specific action.2
-
Position
An EPO control need not be located in the equipment room; a means to reset it is sufficient, subject to a room-design risk assessment.
Stated by NHS England
-
Position
Setting guidance or associated training requirements falls outside the regulator’s powers, so it cannot respond further on those matters.
Stated by Care Quality Commission
-
Concerns raised1
Lack of a system or check to alert ward staff to local mains-power failure
This report raised 6 other concerns. They are not shown here because they do not form part of this recurring concern.
Responses linked to these concernsEach statement is shown once, even when linked to more than one concern.
Actions described in response An action is something a respondent says it has done, is doing, or plans to do in response to the concern raised.3
-
Action
Obtain external electrical-infrastructure advice and use it to design Richmond ADU UPS/IPS backup arrangements.
Stated by St George'S University Hospitals NHS Foundation Trust -
Action
Progress tendering and installation of the Richmond ADU UPS/IPS backup system to alert staff when mains power fails.
Stated by St George'S University Hospitals NHS Foundation Trust -
Action
Consider the adequacy of HTM guidance on alerts relating to power-supply interruptions.
Stated by Department of Health and Social Care
Respondent positions A position is what a respondent says about the concern when they do not describe a specific action.1
-
Position
Existing HTM guidance is considered adequate regarding alerts for interruptions to power supply.