Recurring concern
Unsafe control of electrical systems in prison cells
First reported 11 Feb 2021•Latest report 17 Jan 2024
What this concern includes
Includes failures of controls specifically dedicated to prison-cell electrical safety, including timely remedial maintenance of electrical faults and authorised, risk-assessed and time-limited isolation of cell power.
Not included
- Excludes generic prison maintenance, staffing or lockdown-capacity deficiencies unless they directly concern the safety control of cell electrical systems.
- Excludes general electrical-equipment maintenance outside prison cells.
- Excludes unrelated cell hazards, fire-detection systems, telephones, call bells or other prison safety systems unless the assertion specifically concerns electrical safety of the cell system.
- Excludes the underlying risk of self-harm or fire where no deficiency in a prison-cell electrical safety control is identified.
- Reports
- 2
- Individual concerns
- 2
- Date range
- 2021–2024
- Stated actions
- 1
Distinct published reports
A report can raise multiple concerns
First to latest report issue date
Described in published responses
Reports over time
Reports over time
Reports about this concern issued each year.
* 2026 is projected from reports observed to 7 Sep 2026.
Most frequent recipients
Most frequent recipients
Reports about this concern sent to each recipient.
Concerns and responses across reports
Only concerns grouped under this recurring concern are included. Select any concern, action or position to view the source wording.
-
Concerns raised1
Lack of policy governing the isolation of power to cells
This report raised 9 other concerns. They are not shown here because they do not form part of this recurring concern.
Responses linked to these concernsEach statement is shown once, even when linked to more than one concern.
No linked response statementsNo respondent-stated action or position is linked to these concerns in the published data.
-
Concerns raised1
Delays in remedial maintenance for cell electrical faults during lockdown
Responses linked to these concernsEach statement is shown once, even when linked to more than one concern.
Actions described in response An action is something a respondent says it has done, is doing, or plans to do in response to the concern raised.1
-
Action
Maintain an out-of-hours process for promptly reporting and rectifying cell electricity faults through an on-call facilities officer and Duty Manager escalation.
Stated by Serco Home Affairs, HMP Dovegate
Data last updated 7 September 2026