First report 18 Sep 2014•Latest report 18 Sep 2014
Recipient record
Reports, concerns and published responses
Private and voluntary organisations · Private limited company. This page brings together reports naming this recipient and response statements clearly connected to concerns raised in those reports.
Reports
1
Naming this recipient
Published responses
100%
Found for named reports
Concerns addressed
2
Across all linked responses
Stated actions
1
Described in responses
Reports over time
Reports over time
Reports naming this recipient by issue year.
Evidence profile
Report topics
Share of this recipient’s reports compared with all other recipients.
100%published responses found
1stated actions described
Topic comparisons are not available in the current evidence snapshot.
Concerns and recipient responses
Statements from Sunrise Medical Limited linked to the concerns in each report. Select any concern, action or position to view the source wording.
Manchester South
Concerns raised3
Failure to ensure staff understand and follow hoist safety training
Tendency of sling material to bag at the sides
Lack of clear guidance on calling emergency services and decision-making authority
Responses linked to these concerns
Each statement is shown once, even when linked to more than one concern.
Actions described in response An action is something this recipient says it has done, is doing, or plans to do in response to the concern raised.1
Action
Publish a model-specific Sunrise hoist instruction manual containing sling safety, maintenance and operation guidance.
Stated completedThe respondent said that this action was complete when they made their response on 18 September 2014.
Respondent positions A position is what this recipient says about the concern when it does not describe a specific action.2
Position
If the hoist was an Oxford model no longer supplied, no action can be taken by the supplier.
Unable to actThe respondent said that a constraint prevented them from taking the relevant action.
Position
Existing comprehensive instructions address equipment purchase, maintenance and operation, so no further action is proposed.
Existing arrangements considered sufficientThe respondent said that existing arrangements were sufficient, so no further action was needed.