PFD report

David George White · Prevention of Future Deaths report

Pin Get email alerts Request correction

Issued 1 Aug 2013•South Yorkshire (Eastern)

Report record

Published report and response evidence

This page connects the concerns raised in this report with statements found in recipients’ published responses. A link shows a clear evidence connection; it does not assign responsibility.

View original report
Concerns
0

Raised in this report

Recipients
1

Named on the report

Responses found
1

Of 1 recipient

Stated actions
2

Described in responses

Recipients and published responses

Source document

Full report text

This is the full text from the original published report.

Open published report

Concerns and recipient responses

Select any concern, action or position to view the source wording.

Report evidence summary

No concerns are currently included for this report.

Other statements in published responses

These actions and other statements could not be clearly connected to one concern in this report.

Recipient-stated actions An action is something a recipient says it has done, is doing, or plans to do in response to a concern raised.2

  1. 1

    Install a bend-safety package at Owston, including enhanced markings, road studs, marker posts, and illuminated high-visibility warning signs.

    Stated by City of Doncaster CouncilStated plannedThe respondent said that this action was planned when they made their response on 1 August 2013.
  2. 2

    Carry out general signing and road-marking enhancements along the A19 route between Toll Bar and Askern.

    Stated by City of Doncaster CouncilStated in progressThe respondent said that this action was in progress when they made their response on 1 August 2013.

Recipient positions A position is what a recipient says about a concern when they do not describe a specific action.1

  1. 1

    The planned package of road safety measures is considered sufficient to highlight the bend, so no additional measures are identified.

    Stated by City of Doncaster CouncilExisting arrangements considered sufficientThe respondent said that existing arrangements were sufficient, so no further action was needed.

Source evidence

How this respondent action was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Install a bend-safety package at Owston, including enhanced markings, road studs, marker posts, and illuminated high-visibility warning signs.

Verbatim wording from the response

“Specifically at the referred bend, the completed scheme will comprise of:”

Source location

Response from Doncaster Metropolitan Borough Council
Page 1 · response
Published 1 August 2013

Open published response

Source evidence

How this respondent action was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Carry out general signing and road-marking enhancements along the A19 route between Toll Bar and Askern.

Verbatim wording from the response

“I refer to your letter of 1 August 2013 regarding Rule 43 of the Coroners Rules 1984 and specifically regarding your request to consider whether, within the scheme of work that is planned with a view to reducing road related injuries on the A19 between Askern and Toll Bar, any specific measures should be taken at or on the approach to the bend in the A19 at Owston and, if so, what those measures are to be.”

Source location

Response from Doncaster Metropolitan Borough Council
Page 1 · response
Published 1 August 2013

Open published response

Source evidence

How this respondent position was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

The planned package of road safety measures is considered sufficient to highlight the bend, so no additional measures are identified.

Verbatim wording from the response

“Specifically at the referred bend, the completed scheme will comprise of:”

Source location

Response from Doncaster Metropolitan Borough Council
Page 1 · response
Published 1 August 2013

Open published response
Back to top

Information checked against the published report and official responses · Data reviewed 7 Sep 2026 · About data quality and limitations

Official responses located
1/1

Data last updated 7 September 2026