Issued 17 Feb 2025•Hertfordshire

Report record

Published report and response evidence

This page connects the concerns raised in this report with statements found in recipients’ published responses. A link shows a clear evidence connection; it does not assign responsibility.

View original report
Concerns
4

Raised in this report

Recipients
3

Named on the report

Responses found
3

Of 3 recipients

Stated actions
15

Described in responses

Source document

Full report text

This is the full text from the original published report.

Open published report

Concerns and recipient responses

Select any concern, action or position to view the source wording.

Report evidence summary

Concerns raised4

  1. Failure to implement planned reforms to ASD assessments
  2. Failure of bridge safety measures to meet current guidance for preventing pedestrian jumping or falling
    Part of recurring concern: Inadequate control of falls risksPart of recurring concern: Inadequate controls for fatal falls from bridges
  3. Delays in ASD assessments
Responses linked to these concerns

Each statement is shown once, even when linked to more than one concern.

Actions described in response An action is something a recipient says it has done, is doing, or plans to do in response to a concern raised.11

  1. Action

    Use the inspection findings to assess the feasibility and costs of raising or replacing the parapets and consider the appropriate improvement options.

    Stated by Hertfordshire County CouncilStated plannedThe respondent said that this action was planned when they made their response on 17 April 2025.
  2. Action

    Liaise with Network Rail and undertake Principal Inspections of both bridges to assess their structural condition.

    Stated by Hertfordshire County CouncilStated in progressThe respondent said that this action was in progress when they made their response on 17 April 2025.
  3. Action

    Continue supporting local systems to implement national autism assessment, mental health, and suicide prevention guidance across commissioned services.

    Stated by NHS EnglandStated in progressThe respondent said that this action was in progress when they made their response on 17 April 2025.

Respondent positions A position is what a recipient says about a concern when it does not describe a specific action.6

  1. Position

    Parapet heights cannot safely be raised until inaccessible structural areas are assessed using up-to-date condition information.

    Stated by Hertfordshire County CouncilUnable to actThe respondent said that a constraint prevented them from taking the relevant action.

Source evidence

How this individual concern was interpreted

PFD Monitor created a concise, searchable interpretation from the report wording shown below. Response links show a clear evidence connection; they do not assign responsibility.

PFD Monitor interpretation

Failure to implement planned reforms to ASD assessments

Wider context from the report

“2. That whilst the local mental health Trust has plans to reform the manner in which ASD assessments for patients under their care are undertaken, the implementation of those plans awaits input from the Integrated Care Board. This means that waiting times for ASD assessments in Hertfordshire remain lengthy which in turn gives rise to a risk of future deaths occurring for the reasons set out above. ”

Is this part of a recurring concern?

No recurring-concern membership is currently published.

Open source report

Source evidence

How this individual concern was interpreted

PFD Monitor created a concise, searchable interpretation from the report wording shown below. Response links show a clear evidence connection; they do not assign responsibility.

PFD Monitor interpretation

Failure of bridge safety measures to meet current guidance for preventing pedestrian jumping or falling

Wider context from the report

“3. That the safety measures in place on the ████████ to guard against pedestrians either jumping or falling from the bridge do not meet current guidance, and therefore gives rise to a risk of future deaths occurring. ”

Is this part of a recurring concern?

Yes — Inadequate control of falls risks; Inadequate controls for fatal falls from bridges.

Open source report

Source evidence

How this individual concern was interpreted

PFD Monitor created a concise, searchable interpretation from the report wording shown below. Response links show a clear evidence connection; they do not assign responsibility.

PFD Monitor interpretation

Delays in ASD assessments

Wider context from the report

“1. That, nationally, waiting times for ASD assessments are very long. Such assessments are important in guiding effective care and treatment, as well as being a potential gateway to access other relevant services. This combined with the fact of an increased risk of suicidal behaviour amongst those who receive a diagnosis of ASD, gives rise to a concern that future deaths may occur on account of the delays in ASD assessment. ”

Is this part of a recurring concern?

No recurring-concern membership is currently published.

Open source report

Source evidence

How this individual concern was interpreted

PFD Monitor created a concise, searchable interpretation from the report wording shown below. Response links show a clear evidence connection; they do not assign responsibility.

PFD Monitor interpretation

Lengthy waiting times for ASD assessments in Hertfordshire

Wider context from the report

“2. That whilst the local mental health Trust has plans to reform the manner in which ASD assessments for patients under their care are undertaken, the implementation of those plans awaits input from the Integrated Care Board. This means that waiting times for ASD assessments in Hertfordshire remain lengthy which in turn gives rise to a risk of future deaths occurring for the reasons set out above. ”

Is this part of a recurring concern?

Yes — Unreliable access to timely autism assessment.

Open source report

Source evidence

How this respondent action was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Use the inspection findings to assess the feasibility and costs of raising or replacing the parapets and consider the appropriate improvement options.

Verbatim wording from the response

“To inspect the footbridge and southern road bridge safely, we need Network Rail's permission for a time when the railway is closed and the overhead power lines turned off. We will use the next Principal Inspection to assess the feasibility of raising or replacing the parapets with new, higher versions. We are currently liaising with Network Rail and will undertake the Principal Inspection at the first opportunity. Once this is complete, we will be able to better understand the feasibility and costs of parapet improvements and consider the most appropriate course of action.”

Source location

Response from Hertfordshire Council
Page 2 · response
Published 17 April 2025

Open published response

Source evidence

How this respondent action was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Liaise with Network Rail and undertake Principal Inspections of both bridges to assess their structural condition.

Verbatim wording from the response

“To inspect the footbridge and southern road bridge safely, we need Network Rail's permission for a time when the railway is closed and the overhead power lines turned off. We will use the next Principal Inspection to assess the feasibility of raising or replacing the parapets with new, higher versions. We are currently liaising with Network Rail and will undertake the Principal Inspection at the first opportunity. Once this is complete, we will be able to better understand the feasibility and costs of parapet improvements and consider the most appropriate course of action.”

Source location

Response from Hertfordshire Council
Page 2 · response
Published 17 April 2025

Open published response

Source evidence

How this respondent action was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Continue supporting local systems to implement national autism assessment, mental health, and suicide prevention guidance across commissioned services.

Verbatim wording from the response

“I hope that the publication of the above guidance in 2023 and 2025 provides assurance to the Coroner and Joshua’s family that actions have been taken since Joshua’s death across the NHS to help address the concerns raised. NHS England continues to support local systems to implement the guidance across their commissioned services. Further information on the work and progress of our Learning Disability and Autism Programme can be found here: https://www.england.nhs.uk/learning-disabilities/”

Source location

Response from NHS England
Page 2 · response
Published 17 April 2025

Open published response

Source evidence

How this respondent action was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Develop a care coordinator role to support families through the clinical pathway and keep them informed of progress.

Verbatim wording from the response

“There are different elements of an ASD assessment, and our new model establishes the resources required to operationalise this activity, specifically:”

Source location

Response from Hertfordshire and West Essex ICB
Page 2 · response
Published 17 April 2025

Open published response

Source evidence

How this respondent action was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Provide additional funding and baseline future provider funding to support development of the neurodiversity assessment model.

Verbatim wording from the response

“We are working intensively on these issues to support our providers to deliver safe and timely care, including significant investment in pathways. We have provided additional funding for the work listed above for financial years 2023/24 at circa £3 million and 2024/25 at approximately £4.1 million, further funding of £4.3 million is baselined into providers budgets for coming financial years from 2025/26 to continue to support the development of the model previously mentioned. However, it must be acknowledged that despite all the efforts detailed above it is expected that long waits for assessment will remain without wider national support, given the ongoing rises in demand that are persisting.”

Source location

Response from Hertfordshire and West Essex ICB
Page 3 · response
Published 17 April 2025

Open published response

Source evidence

How this respondent action was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Provide pre- and post-diagnosis support for children, young people and families.

Verbatim wording from the response

“Work has commenced in a measured and stepped way across our service providers. Key elements include:”

Source location

Response from Hertfordshire and West Essex ICB
Page 2 · response
Published 17 April 2025

Open published response

Source evidence

How this respondent action was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Implement a standardised and consistent referral and triage process.

Verbatim wording from the response

“Work has commenced in a measured and stepped way across our service providers. Key elements include:”

Source location

Response from Hertfordshire and West Essex ICB
Page 2 · response
Published 17 April 2025

Open published response

Source evidence

How this respondent action was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Develop a new referral front door to improve referral quality, information collation, follow-up and data collection.

Verbatim wording from the response

“There are different elements of an ASD assessment, and our new model establishes the resources required to operationalise this activity, specifically:”

Source location

Response from Hertfordshire and West Essex ICB
Page 2 · response
Published 17 April 2025

Open published response

Source evidence

How this respondent action was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Continue and develop the Neurodiversity Support Hub and support offer for families and children regardless of diagnosis status.

Verbatim wording from the response

“There are different elements of an ASD assessment, and our new model establishes the resources required to operationalise this activity, specifically:”

Source location

Response from Hertfordshire and West Essex ICB
Page 2 · response
Published 17 April 2025

Open published response

Source evidence

How this respondent action was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Use pathways involving a wider range of clinical and non-clinical staff specialisms to support diagnosis.

Verbatim wording from the response

“Work has commenced in a measured and stepped way across our service providers. Key elements include:”

Source location

Response from Hertfordshire and West Essex ICB
Page 2 · response
Published 17 April 2025

Open published response

Source evidence

How this respondent action was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Establish a combined clinical triage and assessment pathway across NHS provider trusts to optimise clinical resources.

Verbatim wording from the response

“There are different elements of an ASD assessment, and our new model establishes the resources required to operationalise this activity, specifically:”

Source location

Response from Hertfordshire and West Essex ICB
Page 2 · response
Published 17 April 2025

Open published response

Source evidence

How this respondent position was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Parapet heights cannot safely be raised until inaccessible structural areas are assessed using up-to-date condition information.

Verbatim wording from the response

“We explored simple ways to raise the height of the parapets on the footbridge but unfortunately, concluded that this could not be done safely without up-to-date information on the condition of the structure, parts of which are impossible to access”

Source location

Response from Hertfordshire Council
Page 1 · response
Published 17 April 2025

Open published response

Source evidence

How this respondent position was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Closing the footbridge is not considered a safer response because diversion could increase unsafe pedestrian crossings and exacerbate isolation.

Verbatim wording from the response

“We therefore considered an alternative approach of closing the footbridge. This would create a lengthy diversion for pedestrians to access the southern road bridge and an increased risk of pedestrians crossing the dual carriageway at an unsafe location.”

Source location

Response from Hertfordshire Council
Page 2 · response
Published 17 April 2025

Open published response

Source evidence

How this respondent position was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Bridge inspections require Network Rail permission, railway closure and overhead power isolation before feasibility of parapet improvements can be assessed.

Verbatim wording from the response

“To inspect the footbridge and southern road bridge safely, we need Network Rail's permission for a time when the railway is closed and the overhead power lines turned off. We will use the next Principal Inspection to assess the feasibility of raising or replacing the parapets with new, higher versions. We are currently liaising with Network Rail and will undertake the Principal Inspection at the first opportunity. Once this is complete, we will be able to better understand the feasibility and costs of parapet improvements and consider the most appropriate course of action.”

Source location

Response from Hertfordshire Council
Page 2 · response
Published 17 April 2025

Open published response

Source evidence

How this respondent position was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Hertfordshire and West Essex Integrated Care Board is responsible for delivering local autism assessment pathway improvements and providing further information on them.

Verbatim wording from the response

“I note that your Report has also been addressed to Hertfordshire and West Essex Integrated Care Board (ICB). NHS England has been sighted on their response to the Coroner and notes the work being undertaken to make improvements across service providers, with key elements including:”

Source location

Response from NHS England
Page 2 · response
Published 17 April 2025

Open published response

Source evidence

How this respondent position was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

National guidance requires mental-health support and interventions to continue while people await autism assessment, addressing risks from diagnostic delays.

Verbatim wording from the response

“In April 2023, NHS England published the National Framework and Operational Guidance for Autism Assessment Services. This framework sets out a clear expectation that autism assessment pathways must not operate in isolation from wider services. Critically the operational guidance for Integrated Care Boards states:”

Source location

Response from NHS England
Page 1 · response
Published 17 April 2025

Open published response

Source evidence

How this respondent position was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Long ASD assessment waits are expected to remain without wider national support because demand continues to rise.

Verbatim wording from the response

“We are working intensively on these issues to support our providers to deliver safe and timely care, including significant investment in pathways. We have provided additional funding for the work listed above for financial years 2023/24 at circa £3 million and 2024/25 at approximately £4.1 million, further funding of £4.3 million is baselined into providers budgets for coming financial years from 2025/26 to continue to support the development of the model previously mentioned. However, it must be acknowledged that despite all the efforts detailed above it is expected that long waits for assessment will remain without wider national support, given the ongoing rises in demand that are persisting.”

Source location

Response from Hertfordshire and West Essex ICB
Page 3 · response
Published 17 April 2025

Open published response

Other statements in published responses

These actions and other statements could not be clearly connected to one concern in this report.

Recipient-stated actions An action is something a recipient says it has done, is doing, or plans to do in response to a concern raised.4

  1. 1

    Erect suicide-prevention notices on the footbridge and road bridge, signposting people to the Samaritans.

    Stated by Hertfordshire County CouncilStated completedThe respondent said that this action was complete when they made their response on 17 April 2025.
  2. 2

    Publish national guidance requiring continued health support during autism assessment waits and coordinated responses to autistic people’s distress and suicide risk.

    Stated by NHS EnglandStated completedThe respondent said that this action was complete when they made their response on 17 April 2025.
  3. 3

    Operate the Regulation 28 Working Group to discuss reports, share patient-safety learning nationally and regionally, and identify emerging trends requiring review or action.

    Stated by NHS EnglandStated completedThe respondent said that this action was complete when they made their response on 17 April 2025.
  4. 4

    Create and provide a resource pack directing parents and carers to support available while awaiting assessment.

    Stated by NHS Hertfordshire and West Essex Integrated Care BoardStated completedThe respondent said that this action was complete when they made their response on 17 April 2025.

Source evidence

How this respondent action was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Erect suicide-prevention notices on the footbridge and road bridge, signposting people to the Samaritans.

Verbatim wording from the response

“Immediately after Joshua's sad death, we erected notices on the footbridge and road bridge to help deter future suicide attempts by signposting people to the Samaritans. Additionally, we considered what could be done in relation to the heights of the parapets on the bridges. As your report noted, these are lower than the current standards for new bridges. These standards were introduced relatively recently and are not retrospective on existing structures. Many other bridges both locally and nationally have similar or lower parapets than those set out in the current standards.”

Source location

Response from Hertfordshire Council
Page 1 · response
Published 17 April 2025

Open published response

Source evidence

How this respondent action was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Publish national guidance requiring continued health support during autism assessment waits and coordinated responses to autistic people’s distress and suicide risk.

Verbatim wording from the response

“In April 2023, NHS England published the National Framework and Operational Guidance for Autism Assessment Services. This framework sets out a clear expectation that autism assessment pathways must not operate in isolation from wider services. Critically the operational guidance for Integrated Care Boards states:”

Source location

Response from NHS England
Page 1 · response
Published 17 April 2025

Open published response

Source evidence

How this respondent action was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Operate the Regulation 28 Working Group to discuss reports, share patient-safety learning nationally and regionally, and identify emerging trends requiring review or action.

Verbatim wording from the response

“I would also like to provide further assurances on the national NHS England work taking place around the Reports to Prevent Future Deaths. All reports received are discussed by the Regulation 28 Working Group, comprising Regional Medical Directors, and other clinical and quality colleagues from across the regions. This ensures that key learnings and insights around events, such as the sad death of Joshua, are shared across the NHS at both a national and regional level and helps us”

Source location

Response from NHS England
Page 2 · response
Published 17 April 2025

Open published response

Source evidence

How this respondent action was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Create and provide a resource pack directing parents and carers to support available while awaiting assessment.

Verbatim wording from the response

“Additional support for those waiting in Hertfordshire”

Source location

Response from Hertfordshire and West Essex ICB
Page 3 · response
Published 17 April 2025

Open published response
Back to top

Information checked against the published report and official responses · Data reviewed 7 Sep 2026 · About data quality and limitations