PFD report

Christian Gary HINKLEY · Prevention of Future Deaths report

Pin Get email alerts Request correction

Issued 4 Nov 2021•Mid Kent and Medway

Report record

Published report and response evidence

This page connects the concerns raised in this report with statements found in recipients’ published responses. A link shows a clear evidence connection; it does not assign responsibility.

View original report
Concerns
3

Raised in this report

Recipients
1

Named on the report

Responses found
1

Of 1 recipient

Stated actions
6

Described in responses

Recipients and published responses

Source document

Full report text

This is the full text from the original published report.

Open published report

Concerns and recipient responses

Select any concern, action or position to view the source wording.

Report evidence summary

Concerns raised3

  1. Lack of fire-safer cells for prisoners at increased risk of in-cell fire
    Part of recurring concern: Unreliable prison fire detection systems
  2. Failure of prison fire detection systems to reliably detect in-cell fires within a life-saving timescale
    Part of recurring concern: Unreliable prison fire detection systems
  3. Unavailability of timely Fire and Rescue Service attendance at prison cells with firefighting equipment
Responses linked to these concerns

Each statement is shown once, even when linked to more than one concern.

Actions described in response An action is something a recipient says it has done, is doing, or plans to do in response to a concern raised.3

  1. Action

    Deliver the national fire safety improvement programme, including rollout of in-cell fire detection systems across the prison estate.

    Stated by HM Prison and Probation ServiceStated in progressThe respondent said that this action was in progress when they made their response on 11 November 2021.
  2. Action

    Install stand-alone portable fire detection devices in cells without automatic fire detection systems.

    Stated by HM Prison and Probation ServiceStated completedThe respondent said that this action was complete when they made their response on 11 November 2021.
  3. Action

    Commence the scheduled HMP Swaleside fire safety assessment, including installation of in-cell fire detection systems.

    Stated by HM Prison and Probation ServiceStated plannedThe respondent said that this action was planned when they made their response on 11 November 2021.

Respondent positions A position is what a recipient says about a concern when it does not describe a specific action.3

  1. Position

    Existing interim fire measures, including portable detection devices, firefighting equipment, inspections and staff training, address risks pending automatic systems.

    Stated by HM Prison and Probation ServiceExisting arrangements considered sufficientThe respondent said that existing arrangements were sufficient, so no further action was needed.

Source evidence

How this individual concern was interpreted

PFD Monitor created a concise, searchable interpretation from the report wording shown below. Response links show a clear evidence connection; they do not assign responsibility.

PFD Monitor interpretation

Lack of fire-safer cells for prisoners at increased risk of in-cell fire

Wider context from the report

“I am concerned that: (a) The system of fire detection in HM Prisons is currently inadequate and unsafe. This evidence came from MOJ and CPFSI witnesses and was undisputed. (b) Whilst there is a plan to install in-cell automatic fire detectors in all prison cells the MOJ estimates that this may take up to 7 years to complete in 35 prisons across England and Wales (and perhaps longer for others). (c) From the MOJ’s own study in 2007 it is expected that a prisoner in a cell will die within 8 minutes of ignition of an in-cell fire. (d) There is no reasonable prospect of local Fire & Rescue Service firefighters attending the cell with breathing apparatus and firefighting equipment within that timescale. (e) As it stands, and until in-cell fire detectors are installed at prisons, there is a significant risk of death from in-cell fires because the current fire detection systems cannot reliably detect a fire within a timescale that will enable life-saving steps to be taken in time. (f) That risk is further increased for prisoners with a history of suicide/self-harm, barricading and/or arson. (g) The Chief Inspector of the CPFSI tells us that simple measures could be taken to reduce the risk of death by fire in prison, namely adding in-cell fire detectors to a small number of cells in each wing for prisoners (a) on an ACCT, (b) with a history of barricading, (c) with a history of prison fire-setting or (d) with a history of arson, and placing such prisoners in those fire-safer cells. Accordingly, this situation should be reviewed and consideration given as to whether any steps should be taken to reduce the risk of death by cell fires in prisons (as an interim measure before in-cell detection systems are installed across the prison estate). In particular, the suggestion of the Chief Inspector of the CPFSI – highlighted in bold above – should be considered carefully. ”

Is this part of a recurring concern?

Yes — Unreliable prison fire detection systems.

Open source report

Source evidence

How this individual concern was interpreted

PFD Monitor created a concise, searchable interpretation from the report wording shown below. Response links show a clear evidence connection; they do not assign responsibility.

PFD Monitor interpretation

Failure of prison fire detection systems to reliably detect in-cell fires within a life-saving timescale

Wider context from the report

“I am concerned that: (a) The system of fire detection in HM Prisons is currently inadequate and unsafe. This evidence came from MOJ and CPFSI witnesses and was undisputed. (b) Whilst there is a plan to install in-cell automatic fire detectors in all prison cells the MOJ estimates that this may take up to 7 years to complete in 35 prisons across England and Wales (and perhaps longer for others). (c) From the MOJ’s own study in 2007 it is expected that a prisoner in a cell will die within 8 minutes of ignition of an in-cell fire. (d) There is no reasonable prospect of local Fire & Rescue Service firefighters attending the cell with breathing apparatus and firefighting equipment within that timescale. (e) As it stands, and until in-cell fire detectors are installed at prisons, there is a significant risk of death from in-cell fires because the current fire detection systems cannot reliably detect a fire within a timescale that will enable life-saving steps to be taken in time. (f) That risk is further increased for prisoners with a history of suicide/self-harm, barricading and/or arson. (g) The Chief Inspector of the CPFSI tells us that simple measures could be taken to reduce the risk of death by fire in prison, namely adding in-cell fire detectors to a small number of cells in each wing for prisoners (a) on an ACCT, (b) with a history of barricading, (c) with a history of prison fire-setting or (d) with a history of arson, and placing such prisoners in those fire-safer cells. Accordingly, this situation should be reviewed and consideration given as to whether any steps should be taken to reduce the risk of death by cell fires in prisons (as an interim measure before in-cell detection systems are installed across the prison estate). In particular, the suggestion of the Chief Inspector of the CPFSI – highlighted in bold above – should be considered carefully. ”

Is this part of a recurring concern?

Yes — Unreliable prison fire detection systems.

Open source report

Source evidence

How this individual concern was interpreted

PFD Monitor created a concise, searchable interpretation from the report wording shown below. Response links show a clear evidence connection; they do not assign responsibility.

PFD Monitor interpretation

Unavailability of timely Fire and Rescue Service attendance at prison cells with firefighting equipment

Wider context from the report

“I am concerned that: (a) The system of fire detection in HM Prisons is currently inadequate and unsafe. This evidence came from MOJ and CPFSI witnesses and was undisputed. (b) Whilst there is a plan to install in-cell automatic fire detectors in all prison cells the MOJ estimates that this may take up to 7 years to complete in 35 prisons across England and Wales (and perhaps longer for others). (c) From the MOJ’s own study in 2007 it is expected that a prisoner in a cell will die within 8 minutes of ignition of an in-cell fire. (d) There is no reasonable prospect of local Fire & Rescue Service firefighters attending the cell with breathing apparatus and firefighting equipment within that timescale. (e) As it stands, and until in-cell fire detectors are installed at prisons, there is a significant risk of death from in-cell fires because the current fire detection systems cannot reliably detect a fire within a timescale that will enable life-saving steps to be taken in time. (f) That risk is further increased for prisoners with a history of suicide/self-harm, barricading and/or arson. (g) The Chief Inspector of the CPFSI tells us that simple measures could be taken to reduce the risk of death by fire in prison, namely adding in-cell fire detectors to a small number of cells in each wing for prisoners (a) on an ACCT, (b) with a history of barricading, (c) with a history of prison fire-setting or (d) with a history of arson, and placing such prisoners in those fire-safer cells. Accordingly, this situation should be reviewed and consideration given as to whether any steps should be taken to reduce the risk of death by cell fires in prisons (as an interim measure before in-cell detection systems are installed across the prison estate). In particular, the suggestion of the Chief Inspector of the CPFSI – highlighted in bold above – should be considered carefully. ”

Is this part of a recurring concern?

No recurring-concern membership is currently published.

Open source report

Source evidence

How this respondent action was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Deliver the national fire safety improvement programme, including rollout of in-cell fire detection systems across the prison estate.

Verbatim wording from the response

“Her Majesty’s Prison and Probation Service (HMPPS) is committed to fire safety and ensuring that all prison accommodation complies with modern fire safety standards, this is currently being improved through an ambitious national fire safety improvement programme. In 2015/16 HMPPS committed to the Crown Premises Fire Safety Inspectorate that at least 15% of the annual capital maintenance budget would be allocated to fire safety improvement works across the prison estate. We have honoured this commitment each year since and in 2021 the Government agreed to invest £315m into the prison estate in order to tackle the most pressing maintenance issues, including that of the introduction of in-cell fire detection systems.”

Source location

2021-0376-Response-from-HMPPS_Published
Page 1 · response
Published 11 November 2021

Open published response

Source evidence

How this respondent action was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Install stand-alone portable fire detection devices in cells without automatic fire detection systems.

Verbatim wording from the response

“Stand-alone portable fire detection devices are currently installed for all cells that do not have the automatic fire detection systems, including at HMP Swaleside. These provide an interim fire detection solution, in accordance with the fire safety regulation requirements. All prisons across the estate have also been provided with an increased number of water mist firefighting equipment and portable smoke ventilation fans to assist smoke disbursement during fire incidents. Access to fire ignition sources will remain prohibited with electrical items removed from possession when found to have been tampered with.”

Source location

2021-0376-Response-from-HMPPS_Published
Page 2 · response
Published 11 November 2021

Open published response

Source evidence

How this respondent action was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Commence the scheduled HMP Swaleside fire safety assessment, including installation of in-cell fire detection systems.

Verbatim wording from the response

“There are currently fire safety improvement programmes underway at 35 sites across the prison estate. The work begins with a full assessment of each establishment, many of which require the installation of a full and updated fire detection system before the in-cell fire detectors can be installed. The start date for the fire safety assessment to commence at HMP Swaleside, which will include the installation of the in-cell detections, is currently scheduled to be in December 2022.”

Source location

2021-0376-Response-from-HMPPS_Published
Page 2 · response
Published 11 November 2021

Open published response

Source evidence

How this respondent position was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Existing interim fire measures, including portable detection devices, firefighting equipment, inspections and staff training, address risks pending automatic systems.

Verbatim wording from the response

“For the prisons where the in-cell fire detection systems are not yet installed, there are a number of interim safety measures in place to reduce the risks of cell fires. In April 2021, annual risk based inspection programmes were introduced which are conducted by the HMPPS National Fire Safety Team who review fire safety measures in each prison. This includes reviewing the provision of fire safety equipment, staff training and compliance and the Arson Reduction Strategy of each prison to identify any fire safety risks and any protective measures that may be required to address those risks.”

Source location

2021-0376-Response-from-HMPPS_Published
Page 2 · response
Published 11 November 2021

Open published response

Source evidence

How this respondent position was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Interim installation in selected cells is not feasible because it would be costly, complex and delay the overall fire safety programme.

Verbatim wording from the response

“While it has been reviewed whether in-cell fire detectors could be added to a small number of cells for prisoners that pose a higher risk of self-harm, barricading and fire setting, as an interim measure, this is unfortunately not feasible. Given that a complete new fire system will be required in many prisons across the estate before the in cell detectors can be installed, the workmanship and equipment required to install even a small number of cells for each prison would be significant. The work would then have to resume at a later date to complete the remaining cells and this would be costly and would delay the completion of the overall fire safety improvement programme.”

Source location

2021-0376-Response-from-HMPPS_Published
Page 2 · response
Published 11 November 2021

Open published response

Source evidence

How this respondent position was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Earlier national installation cannot be completed because complexity, investment, resources, disruption and security constraints require five to seven years.

Verbatim wording from the response

“The rollout of the automatic fire safety systems nationally relies on a sustained level of investment and on the availability of resources to ensure that there is minimal disruption to the prison regimes. Fire safety systems are costly and complex to install and there can be delays in these works due to important measures to maintain the safety of staff and prison residents and also to maintain the overall security of the prison. It can therefore take a number of years to install the full system at a single establishment. Given the number of prisons nationally that require this work and the challenges in doing this, the overall”

Source location

2021-0376-Response-from-HMPPS_Published
Page 1 · response
Published 11 November 2021

Open published response

Other statements in published responses

These actions and other statements could not be clearly connected to one concern in this report.

Recipient-stated actions An action is something a recipient says it has done, is doing, or plans to do in response to a concern raised.3

  1. 1

    Conduct annual risk-based fire safety inspections at each prison to review equipment, training, compliance and arson-risk controls.

    Stated by HM Prison and Probation ServiceStated completedThe respondent said that this action was complete when they made their response on 11 November 2021.
  2. 2

    Revise prison officer Cell Fire Response training to cover obstructed inundation ports and use of observation panels as alternative water-mist access points.

    Stated by HM Prison and Probation ServiceStated completedThe respondent said that this action was complete when they made their response on 11 November 2021.
  3. 3

    Provide prisons with additional water-mist firefighting equipment and portable smoke-ventilation fans.

    Stated by HM Prison and Probation ServiceStated completedThe respondent said that this action was complete when they made their response on 11 November 2021.

Source evidence

How this respondent action was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Conduct annual risk-based fire safety inspections at each prison to review equipment, training, compliance and arson-risk controls.

Verbatim wording from the response

“For the prisons where the in-cell fire detection systems are not yet installed, there are a number of interim safety measures in place to reduce the risks of cell fires. In April 2021, annual risk based inspection programmes were introduced which are conducted by the HMPPS National Fire Safety Team who review fire safety measures in each prison. This includes reviewing the provision of fire safety equipment, staff training and compliance and the Arson Reduction Strategy of each prison to identify any fire safety risks and any protective measures that may be required to address those risks.”

Source location

2021-0376-Response-from-HMPPS_Published
Page 2 · response
Published 11 November 2021

Open published response

Source evidence

How this respondent action was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Revise prison officer Cell Fire Response training to cover obstructed inundation ports and use of observation panels as alternative water-mist access points.

Verbatim wording from the response

“The prison officer Cell Fire Response training was also revised in December 2021 to include a narrative and a practical scenario for where the cells inundation port is seized or obstructed with the observation panel used as the secondary inundation point. The use of the observation panel aperture provides prison officers with an effective alternative route to inundate the cell with water mist.”

Source location

2021-0376-Response-from-HMPPS_Published
Page 2 · response
Published 11 November 2021

Open published response

Source evidence

How this respondent action was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Provide prisons with additional water-mist firefighting equipment and portable smoke-ventilation fans.

Verbatim wording from the response

“Stand-alone portable fire detection devices are currently installed for all cells that do not have the automatic fire detection systems, including at HMP Swaleside. These provide an interim fire detection solution, in accordance with the fire safety regulation requirements. All prisons across the estate have also been provided with an increased number of water mist firefighting equipment and portable smoke ventilation fans to assist smoke disbursement during fire incidents. Access to fire ignition sources will remain prohibited with electrical items removed from possession when found to have been tampered with.”

Source location

2021-0376-Response-from-HMPPS_Published
Page 2 · response
Published 11 November 2021

Open published response
Back to top

Information checked against the published report and official responses · Data reviewed 7 Sep 2026 · About data quality and limitations

Official responses located
1/1

Data last updated 7 September 2026