First report 20 Feb 2025•Latest report 20 Feb 2025
Recipient record
Reports, concerns and published responses
Private and voluntary organisations · Private limited company. This page brings together reports naming this recipient and response statements clearly connected to concerns raised in those reports.
Reports
1
Naming this recipient
Published responses
100%
Found for named reports
Concerns addressed
1
Across all linked responses
Stated actions
4
Described in responses
Reports over time
Reports over time
Reports naming this recipient by issue year.
Evidence profile
Report topics
Share of this recipient’s reports compared with all other recipients.
100%published responses found
4stated actions described
Topic comparisons are not available in the current evidence snapshot.
Concerns and recipient responses
Statements from Hatton Traffic Management Limited linked to the concerns in each report. Select any concern, action or position to view the source wording.
Essex
Concerns raised4
Inadequate Code of Practice guidance for calculating street works distances where standard reference points or markings are unavailable or variable
Difficulties in calculating distances for roadworks set up in darkness
Failure to place road works warning signs without obscuring visibility of joining traffic
Absence of a requirement to notify fatalities within roadworks on permit applications
Responses linked to these concerns
Each statement is shown once, even when linked to more than one concern.
Actions described in response An action is something this recipient says it has done, is doing, or plans to do in response to the concern raised.4
Action
Devise and roll out a toolbox talk addressing sight-line issues and the procedure changes across the business.
Stated completedThe respondent said that this action was complete when they made their response on 25 February 2025.
Action
Complete a full review of emergency works procedures.
Stated completedThe respondent said that this action was complete when they made their response on 25 February 2025.
Action
Roll out new detailed design layouts and sign-placement guidance for all traffic-light schemes and road speeds.
Stated completedThe respondent said that this action was complete when they made their response on 25 February 2025.
Action
Add a process-flow question requiring operatives to record whether signage sight lines have been checked and assessed as appropriate.
Stated completedThe respondent said that this action was complete when they made their response on 25 February 2025.