Inner North London
Concerns raised6
Failure of method statements, risk assessments and lift plans to address changed landing-fitting processes
Insufficient process understanding among personnel responsible for planning and approving landing-fitting work
Unavailability of an appropriate plan for basement landing fitting
Failure to specify the correct landing orientation for tag-line tilting
Failure to include stop instructions for unsuccessful positive fixings during landing fitting
Failure to identify the need for a task-specific landing-fitting plan during drafting and approval
No linked response statementsNo action or position from this recipient is clearly linked to the concerns in this report.