PFD report

Karen Ann Thorne · Prevention of Future Deaths report

Pin Get email alerts Request correction

Issued 11 Nov 2016•Manchester West

Report record

Published report and response evidence

This page connects the concerns raised in this report with statements found in recipients’ published responses. A link shows a clear evidence connection; it does not assign responsibility.

View original report
Concerns
2

Raised in this report

Recipients
1

Named on the report

Responses found
1

Of 1 recipient

Stated actions
0

Described in responses

Recipients and published responses

Source document

Full report text

This is the full text from the original published report.

Open published report

Concerns and recipient responses

Select any concern, action or position to view the source wording.

Report evidence summary

Concerns raised2

  1. Delays in reporting neuroradiology and radiology
    Part of recurring concern: Failure to ensure clinical investigation results are reliably available, interpreted and acted uponPart of recurring concern: Unreliable radiology processes for communicating findings and initiating required follow-upPart of recurring concern: Unreliable timeliness of radiology imaging and reporting
  2. Insufficient radiologist training capacity
    Part of recurring concern: Insufficient medical staffing capacity for timely patient carePart of recurring concern: Insufficient radiology workforce capacity for timely imaging and interpretation
Responses linked to these concerns

Each statement is shown once, even when linked to more than one concern.

Respondent positions A position is what a recipient says about a concern when it does not describe a specific action.2

  1. Position

    Some matters raised in the concerns are the responsibility of the relevant NHS Trust rather than the Department of Health.

    Stated by Department of Health and Social CareRedirects responsibilityThe respondent said that another organisation was responsible for deciding or taking action.

Source evidence

How this individual concern was interpreted

PFD Monitor created a concise, searchable interpretation from the report wording shown below. Response links show a clear evidence connection; they do not assign responsibility.

PFD Monitor interpretation

Delays in reporting neuroradiology and radiology

Wider context from the report

“1. During the Inquest evidence was heard that:- i. There are delays in reporting neuroradiology within the Salford Royal NHS Foundation Trust and at the present time the longest wait is 60 days, which is a slight improvement from the end of 2015 when the Scan conducted on the Deceased was not reported for 65 days but a delay of 60 days is still unacceptable. ii. There is an increasing demand for neuroradiology, and radiology in general, and there is a national shortage of Radiologists. iii. The delay in reporting radiology is of greater concern in cases where a patient is receiving treatment on a regular basis, namely every 28 days in the case of the Deceased, and the Scans are not reported for a period in excess of 60 working days, during which time the Deceased received 2 or 3 additional Natalizumab infusions, which would have been stopped had the Scan been reported and identified PML before the next infusion. iv. Evidence was given at the Inquest, on the basis of information received from the Royal College of Radiologists, that the national shortage of Radiologists was due to the fact that there are a fixed number of training positions for Radiologists each year and the number is insufficient to produce the number of Radiologists required to give an appropriate service and to report radiology within a reasonable, necessary and expected time period. The information referred to the fact that there was no shortage of clinicians prepared to train as Radiologists and that there were more applicants than training positions. The evidence given to the Inquest was that an increase in the number of training positions would increase the number of Radiologists to address the national shortage of Radiologists, which is creating the delays in reporting radiology and delays in the diagnosis of conditions requiring either immediate treatment or the cessation of treatment with recognised complications. 2. I request you to consider the above concerns in relation to a national shortage of Radiologists and to review the number of training positions to address the national shortage of Radiologists and to address delays in the reporting of radiology and the diagnosis of disease, either requiring treatment or the cessation of treatment. ”

Is this part of a recurring concern?

Yes — Failure to ensure clinical investigation results are reliably available, interpreted and acted upon; Unreliable radiology processes for communicating findings and initiating required follow-up; Unreliable timeliness of radiology imaging and reporting.

Open source report

Source evidence

How this individual concern was interpreted

PFD Monitor created a concise, searchable interpretation from the report wording shown below. Response links show a clear evidence connection; they do not assign responsibility.

PFD Monitor interpretation

Insufficient radiologist training capacity

Wider context from the report

“1. During the Inquest evidence was heard that:- i. There are delays in reporting neuroradiology within the Salford Royal NHS Foundation Trust and at the present time the longest wait is 60 days, which is a slight improvement from the end of 2015 when the Scan conducted on the Deceased was not reported for 65 days but a delay of 60 days is still unacceptable. ii. There is an increasing demand for neuroradiology, and radiology in general, and there is a national shortage of Radiologists. iii. The delay in reporting radiology is of greater concern in cases where a patient is receiving treatment on a regular basis, namely every 28 days in the case of the Deceased, and the Scans are not reported for a period in excess of 60 working days, during which time the Deceased received 2 or 3 additional Natalizumab infusions, which would have been stopped had the Scan been reported and identified PML before the next infusion. iv. Evidence was given at the Inquest, on the basis of information received from the Royal College of Radiologists, that the national shortage of Radiologists was due to the fact that there are a fixed number of training positions for Radiologists each year and the number is insufficient to produce the number of Radiologists required to give an appropriate service and to report radiology within a reasonable, necessary and expected time period. The information referred to the fact that there was no shortage of clinicians prepared to train as Radiologists and that there were more applicants than training positions. The evidence given to the Inquest was that an increase in the number of training positions would increase the number of Radiologists to address the national shortage of Radiologists, which is creating the delays in reporting radiology and delays in the diagnosis of conditions requiring either immediate treatment or the cessation of treatment with recognised complications. 2. I request you to consider the above concerns in relation to a national shortage of Radiologists and to review the number of training positions to address the national shortage of Radiologists and to address delays in the reporting of radiology and the diagnosis of disease, either requiring treatment or the cessation of treatment. ”

Is this part of a recurring concern?

Yes — Insufficient medical staffing capacity for timely patient care; Insufficient radiology workforce capacity for timely imaging and interpretation.

Open source report

Source evidence

How this respondent position was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Some matters raised in the concerns are the responsibility of the relevant NHS Trust rather than the Department of Health.

Verbatim wording from the response

“Some of the matters you raise are for the Trust. For the concerns you raise about the shortage of radiologists, Department of Health officials have contacted Health Education England about its plans to recruit more trainees into radiology. I understand Health Education England is working in partnership with NHS England and a range of professional bodies to develop a shared vision and strategy for the diagnostics workforce. Clinical Radiology is a priority area.”

Source location

2016-0408-Response-by-Department-of-Health
Page 1 · response
Published 11 November 2016

Open published response

Source evidence

How this respondent position was interpreted

PFD Monitor created a concise, searchable interpretation from the published response wording shown below.

PFD Monitor interpretation

Responsibility for addressing radiologist shortages and developing diagnostic workforce plans lies with Health Education England and its partners.

Verbatim wording from the response

“Some of the matters you raise are for the Trust. For the concerns you raise about the shortage of radiologists, Department of Health officials have contacted Health Education England about its plans to recruit more trainees into radiology. I understand Health Education England is working in partnership with NHS England and a range of professional bodies to develop a shared vision and strategy for the diagnostics workforce. Clinical Radiology is a priority area.”

Source location

2016-0408-Response-by-Department-of-Health
Page 1 · response
Published 11 November 2016

Open published response
Back to top

Information checked against the published report and official responses · Data reviewed 7 Sep 2026 · About data quality and limitations

Official responses located
1/1

Data last updated 7 September 2026